Capital Projects Underway

Home Facilities Operations Program Additional Info

CURRENTLY UNDERWAY:  Progress report on capital projects underway

Here is an update on the projects currently underway (Pictures are available on bold marked projects links below in list):

Leonard & Marjorie Williams Family Scout Reservation Site Plan - .pdf file (Adobe Reader) 04/2007 copy

CFCBSA Camps Weblog  - Blogging resource for additional Capital Building Project Information.

 
Central Florida Council BSA Capital Building Projects List - As of March 26, 2008
PHASE 1 Capital Projects Current Status Assignment - 
Renovation Campsite Shelters -2/08  Pictures:  Campsite Activity Shelters Construction - 2/08
Campsite 11 Activity Shelter Construction Commencement started John Murphy
Campsite 14 Activity Shelter Construction Commencement started John Murphy
Campsite 16 Activity Shelter Construction Commencement started John Murphy
New Campsites - 2/08        Pictures:  LATRINE Construction -3/26/08   Campsite Activity Shelters Construction3/26/08
New Campsites Sewer System Engineer Planning Gregg Harkness
Campsite H Latrine Construction Commencement started John Murphy
Campsite H Activity Shelter Construction Commencement started John Murphy
Campsite H Other Not started  
Campsite I Latrine Construction Commencement started John Murphy
Campsite I Activity Shelter Construction Commencement started John Murphy
Campsite I Other Not started  
Campsite L Latrine Construction Commencement started John Murphy
Campsite L Activity Shelter Construction Commencement started John Murphy
Campsite L Other Not started  
Campsite M Latrine Construction Commencement started John Murphy
Campsite M Activity Shelter Construction Commencement started John Murphy
Campsite M Tent Pads Not started  
Campsite M Other Not started  
Other Capital Phase 1 Projects
Archway - Gateway - 3/26/08 Construction Commencement started Tim Keating, Matt 
Ground Sign - Maggie Jones 2/08 Lake County Planning & Design Mike Harding, Matt
Shooting Sports Activity Pavilion3/26/08 Construction Commencement started John Murphy
Chapel 1/08 Bob Burke designing plans Bob Burke
Alpine Tower 1/08 Open program and in operation Camp Program
Scout Ranch Evasive Plant removal & planning stage for usage Claire, Rick, Harry, Bob,
Camp Roper 1/08 Work projects to set up as Primitive Camps Ryan
Council Ring AV/Sound Upgrade 3/26/08 Upgrading the AV/Sound at Council Ring Mark & Todd
Wildlife Plot Not started  
     
PHASE 2 & 3
Rezoning Not started  
8 Additional New Campsites Not started  
9 Replacement Campsite Shelters Not started  
Administration Offices - 1/08 Bob Burke designing plans & seeking funding Bob Burke
Bunkhouse - 1/08 Bob Burke designing plans & seeking funding Bob Burke
New Downtown Camp Pool - 1/08 Concept planning & seeking funding Jeff Kosik & Gary Brewer
Skills Activity Shelter - 1/08 Gary Brewer seeking funding Gary Brewer
Adventure Camp Infrastructure Seeking Electrical Power estimates Brian, Bob & Todd
Adventure Camp Latrine Not started  
Adventure Camp Activity Shelter Not started  
Adventure Camp Summit & Climb Not started  
Adventure Camp COPE Ashelter Not started  
Adventure Camp Obstacle Course Not started  
Adventure Camp Lumberjack Not started  
Adventure Camp Wilderness Surv. Not started  
New Quartermaster Hut Not started  
Downtown Camp Electrical Bury Received estimate & seeking funding Brian, Bob & Todd
8 New Family Camp Cabins Not started  
 
If you have questions or comments, please feel free to e-mail matt@camplanoche.com.  I will be more than happy to past on these questions and comments to our Physical Resource Committee (Board and Council Volunteers).

CFCBSA Camps Weblog

Return to Facilities Page